The subject of the contract was Investor’s supervision on modernization of the “CKW Sułkowski” Center.
Characteristics of the building after modernization:
Building:
fully air-conditioned building with luxury apartments
Destiny:
multifunctional conference center
Additionally:
bowling, foyer and lobby bar
Surface after extention:
3 783 m²
Cubature:
15 300 m³
Sułkowski - Boszkowo
Scope of work
Investor’s Supervision
endering procedure: preparation of tender documents, basic provisions of the contract, including five major procurement packages – General Contractor, the Contractor of sanitary works and electrical works, the Contractor LV work, the Contractor of finishing work and the Contractor of road works
Inspector supervision of the implementation of construction
The procedure for acceptance control, with final acceptances work of all Contractors