The subject of the contract was investor's supervision over the construction of a large-area Castorama store with associated infrastructure, a warehouse and an office part in the Shopping Park Siedlce.
Characteristics
Building:
a compact block consisting of a 1-storey sales hall and a 2-storey office and social part
Construction:
reinforced concrete pillar structure, steel roof structure, office part in monolithic reinforced concrete structure
Zones of the hall:
main hall, a social and office part and a warehouse a delivery area available for vans with an unloading shelter customer area with a multibay car park for passenger cars with access to the store entrance
Total area:
12 242 m2
Usable area:
10 457 m2
Total height:
9,7 m / 2 storeys
Castorama Siedlce
Scope of works
Project coordination in the scope of all design and construction works carried out at this investment.
Comprehensive investor supervision of all industries during construction, including, among others, representing the Investor at meetings with Designers, controlling work on the construction site, checking the completeness of project documentation, consulting and opinions on formal, technical and economic matters, ongoing verification of the progress of works at the construction site.
In addition, coordinating the flow of information between the General Contractor and the Investor as well as maintaining compliance of construction and OHS procedures with the Investor's requirements and standard through the Project Administrator on behalf of KKBud.
Customer
Castim Polska Sp. z o.o.
Opening
14 October 2020
Applied solutions and installations
external water supply system
internal and external sanitary and rainwater sewage system
internal installation of cold, hot water and circulation
installation of indoor hydrants
gas boiler plant technology
central heating and technological heat installation
internal gas installation
ice water installation
installation of mechanical ventilation and air conditioning of selected rooms